The facility partnered with an international nuclear energy services company to renovate and qualify four 12-foot, 24-ton pumps.
AREVA & Dominion Virginia Power
12/19/2016
For decades, the U.S. fleet of nuclear power facilities has efficiently and reliably generated low-carbon electricity. Inside each facility, reactor coolant pumps (RCPs) and other components play a critical role in creating this electricity. This equipment, however, operates for extended periods of time under harsh conditions. Eventually, these components need to be refurbished or replaced. The nuclear industry is constantly exploring innovative and efficient ways to complete these replacements and to ensure operational excellence. In 2015, Dominion Virginia Power completed one of the largest RCP refurbishment projects in the U.S. at the Surry Power Station in southeastern Virginia.
Image 1. With the old RCP removed, a field engineer places a foreign material exclusion (FME) shield over the pump housing. (Images courtesy of AREVA)
The project scope included five pump replacements.
The facility partnered with an international nuclear energy services company to renovate and qualify four 12-foot, 24-ton pumps, including two from Dominion’s closed Kewaunee Power Station in Wisconsin. One additional pump previously refurbished by the nuclear energy services company was used to complete the project scope.
Image 2. The RCP shaft is placed in the lathe to measure total indicated runouts (TIR). The TIR indicates the trueness of the shaft. This process ensures that both ends of the shaft rotate on the same axis.
Deciding to Replace RCPs
In 2014, intergranular stress corrosion cracking (IGSCC) was found on turning vane bolts in a U.S. power plant. These bolts secure the turning vane diffuser assembly inside the RCP, located above the pump impeller. The original equipment manufacturer identified a problem with pumps manufactured with 1-inch-diameter turning vane bolts. After evaluating this issue, Dominion decided to upgrade and replace all its facilities’ RCPs that contained 1-inch-diameter turning vane bolts. At Surry, five RCPs were affected: two in Unit 1 and three in Unit 2. Dominion contracted the nuclear energy services company to refurbish the RCPs, including replacing the turning vane bolts. This work was performed in Unit 1 during the spring 2015 outage and Unit 2 during the fall 2015 outage.Image 3. Over time, normal wear occurs in the operation of the impeller. Here, the refurbished impeller is in its final balance operation.
Overcoming Obstacles to RCP Refurbishment
With an aggressive outage schedule, spare pumps had to be obtained in 10 months—a monumental task when, historically, lead times to secure RCPs were two to three years. Faced with such a challenge, the nuclear energy services company looked into reclaiming two RCPs from Dominion’s retired Kewaunee plant in Wisconsin and refurbishing them to like-new conditions. This innovative idea presented significant challenges that needed to be addressed before the company could proceed with purchasing the pumps from Kewaunee:- Ownership: The ownership of the pumps had to be resolved. Kewaunee is part of the unregulated business at Dominion, but Surry is a regulated business facility. Moving assets from unregulated to regulated facilities required meeting certain regulations.
- Condition: The team had to determine whether the pumps were in a condition to support more than 20 years of service at Surry after operating for more than 30 years at Kewaunee. To be refurbished for another facility, the pumps could not be degraded.
- Codes and licensing: American Society of Mechanical Engineers (ASME) requirements vary from plant to plant based on state and date of construction. As a result, the team had to evaluate each state’s codes and standards to determine if the Kewaunee pumps were built to code requirements that satisfy those governing Surry.
- Physical interchangeability: A number of physical requirements had to be evaluated, including the size of the Kewaunee pump and the Surry pump casing, the Kewaunee pump flow rate and pressure compared with the Surry pump, the location of the interface for the motor (coupling, motor stand bolts), and the location of the piping connections (seal water, cooling water).
Image 4. The FME cover is placed over the pump impeller after the balance is complete.
The nuclear energy services company performed a detailed engineering study that confirmed that the Kewaunee pumps were a safe and reliable solution for installation at the Surry station. The team then decided to proceed with the purchase.
Undertaking the Refurbishment Project
The RCP refurbishment project included replacement of the shafts, impellers, couplings, bearings and all bolting on the pumps. The accelerated delivery schedule required the nuclear energy services company to manufacture these replacement parts in less than six months—a task that normally takes one to two years. Alongside the engineering and manufacturing efforts, the company’s field implementation teams planned the complex logistics of replacing multiple RCPs during a normal maintenance outage. The company’s pump and motor field service team and Surry’s maintenance technicians completed extensive mock-up training exercises, which were integral to the planning and preparation. This also led to the development of new and improved tooling and equipment.Image 5. The refurbished main flange is installed in the up-ender and ready for pump reassembly.
With these investments in planning and preparation, the replacement was a success. A key factor was close coordination among the teams from the Surry station, Dominion engineering in Innsbrook, Virginia, the nuclear energy services company’s pump and motor service center in Lynchburg, Virginia, and the company’s manufacturing facility in Jeumont, France.
Identifying & Integrating Lessons Learned
Project personnel learned several lessons throughout the process of refurbishing and qualifying the RCPs, including opportunities to integrate safety improvements, enhance outage excellence and innovate technologies in preparation for the next scope of work.Maintaining a Clear Focus on Safety
Five RCPs were refurbished and installed without any safety issues, personal contamination events or human performance errors. This performance is attributed to the team’s rigorous focus on safety, which was the No. 1 priority during the entire project. Using full-scale mock-ups for the RCP and machining activities, both management and crew members trained and performed all tasks based on field-like conditions. Ensuring team members experience radiation doses well within regulated limits is a key aspect of every project plan. Practicing critical tasks where expected radiation exposure is higher, such as removing and installing the RCP and the shield plug access cover on the mock-ups, allowed the team to explore best practices to reduce process time and to integrate new techniques that resulted in lowering expected REM dose exposure, also called achieving dose savings. REM is a standard unit of measurement for radiation dosage; it combines the amount of energy produced by the radioactive material with the medical effects of the given type of radiation.Image 6. Engineers hook rigging to the pump for transport.
This focus on safety resulted in measurable reductions in the radiation levels the team experienced during each refurbishment. The dose savings from the first pump to the last were 1.521 REM, equivalent to a dose savings of approximately 76 milli-REM per individual per RCP outage.
Enhancing Outage Excellence
Because timeframes for outages are decreasing at plants across the country, largely for economic reasons, the project team identified numerous ways to improve processes, incorporate best practices and develop solutions for equipment efficiency. By continually improving, the team maintained the outage schedule and stayed within budget. Improved communication between the field and project teams was critical to the success of the project. A key lesson learned and adopted early in the process was to organize the entire project team in the same working area. Having a unified base location eliminated communication delays and improved handoffs between teams.Image 7. The refurbished pump is moved to a shipping cask.
In addition, remote video monitoring and communication equipment supported inspections and eliminated the need for multiple oversight personnel.
As a result, the team could provide status updates and troubleshoot issues in real time in the field with outside support.
Integrating Innovative Processes & Technologies
Improved processes and innovative technologies allowed the team to be proactive, which increased productivity and reduced critical path time and impacts to the schedule and other work groups. Innovative solutions for transporting and installing components also improved overall project performance. For instance, the nuclear energy services company designed a shielded transport RCP cask with one hook to up-end the large component. The cask’s smaller footprint and easy lift design simplified the process of repositioning the component, reducing polar crane and critical path time by eight hours per pump. Engineering innovations helped configure the unique style of Kewaunee’s pumps for Surry. Flow curves, piping configurations and thermal monitoring systems all required attention. Dominion worked with the nuclear energy services company to fabricate new shafts and impellers for the pumps to achieve flow requirements. Because of the RCP’s complex geometry, state-of-the-art digital measurement technology was used to measure the different dimensions of the pump components. Three-dimensional overlays of the new and old pumps identified possible deviations with more accuracy and speed than was previously possible through manual measurements.Image 8. The refurbished pump is placed in the cask.
Using these new processes and equipment allowed for a reduced critical path schedule. Standard RCP replacements can extend an outage by as much as seven days. By implementing lessons learned from this RCP project, others in the industry can now replace multiple pumps within a normal maintenance outage schedule.