In this month’s Pumps & Systems column, we will look at how simulating a large heat transfer system balance found in many industrial plants can be used to streamline plant operations. The system balancing ensures each heat exchanger is receiving the proper flow rate and pressure needed for the system to operate properly. Early in my career, I worked as a startup and test engineer at Millstone Power Station Unit 2 for Northeast Utilities. Millstone 2 was a Combustion Engineering 870 MWe nuclear power plant, and was much larger that the plants I had worked on in the Navy. One of the first preoperational tests I was involved in was balancing the Component Cooling Water (CCW) system for Millstone Unit 2. The system had a normal operating mode in which cooling water was supplied to various heat generating equipment in the reactor compartment and auxiliary machinery spaces. The system had Nuclear Regulatory Commission (NRC) licensing requirements to be operational when the reactor was producing power and when it was shut down. In addition, the system was designed to automatically provide cooling water to specific equipment during an off normal (post-accident) condition. Once all the equipment in the CCW system was tested, the entire system was placed in operation and then balanced so that each heat exchanger received the designed flow rate and pressure required for proper system operation. The system also had to be balanced for off-normal operation in the event of an accident. The CCW system was large, encompassing multiple pumps, heat exchangers, control valves and pipelines covering most of the plant. Since this was a safety-related system, the CCW balancing had to be completed prior to the NRC issuing an operating license, which would allow the loading of radioactive fuel. The test was planned to take approximately 10 days, with the actual plant testing to occur during the swing shift and midnight shift. The testing required most of the operational staff to operate the equipment, and a group of test engineers to set the balancing valves to their prescribed positions. After all the balancing valves were set to the prescribed positions, plant test data was collected for further analysis.
Pump System Improvement
Engineered Software Inc
11/20/2017
Figure 1. The component cooling water (CCW) system (Courtesy of the author)
The results of the nightly tests were compiled and sent to Bechtel Power in Gaithersburg Maryland, which was the A&E firm for Unit 2. Their engineers reviewed the results to determine the flow rates through each of the CCW heat loads. Based on the test results they would generate a new table with the adjusted valve positions for each balancing valve to achieve the designed flow rate.
The CCW system was a network of looped loads, and changing the position of any of the balancing valves affected the flow rates to all the loads. Each night, we would adjust the balancing valves in the CCW system to the new positions and then re-run the test, compile the results and submit them to the engineers in Bechtel.
The above process was continued until the system was balanced and the flow rate through each heat exchanger was at its designed value. This test took approximately eight days to complete with many different iterations. Since it needed to be complete prior to the issuance of the plants operating license by the NRC, it received the highest level of interest and scrutiny from the management team.
To read more Pump System Improvement columns, click here.