For decades, paper mills along a section of the Kalamazoo River had dumped polychlorinated biphenyls (PCBs) into the waterway. The river flow then took the contamination far downstream from the original source, making a large swath of southwest Michigan subject to contamination. PCBs are linked to an increased cancer risk, compromised immune systems in people and animals, and impaired memory/cognition. PCB exposure can occur when people come into direct contact with contaminated soil or water or eat fish from an affected waterway. While the use of PCBs stopped in the late 1970s, the contamination has remained in the river bed and surrounding area. The federal Environmental Protection Agency (EPA), in conjunction with the Michigan Department of Environmental Quality, declared an 80-mile stretch of the Kalamazoo River as part of a superfund site in 1990. Superfund sites are polluted locations requiring a long-term response to clean up hazardous material contaminations.
The project was finished ahead of schedule and $4 million under budget.
03/01/2016
Image 1. An aerial view of the Portage Creek project shows pumps with sound-attenuated enclosures. (Courtesy of Cornell Pump Company)
The Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) is a federal law designed to clean up sites contaminated with hazardous substances as well as broadly defined "pollutants or contaminants," and it gives the EPA the authority to clean up locations such as the Kalamazoo River.
As part of that Kalamazoo River superfund site cleanup, a two-and-a-half mile stretch of Portage Creek, in the Edison neighborhood of Kalamazoo, required remediation for PCBs. During this process, more than 19,000 cubic yards of PCB-contaminated soil and sediment were removed. To facilitate the cleanup, Portage Creek was dammed and diverted in sections. The sections furthest upstream were treated first so the contamination could move downstream, allowing areas cleaned above the existing contamination to remain clean.
Image 2. This shows water from Portage Creek returning from the bypass area through pumps upstream, with shoring material in the background used to keep remediate area clean.
The project used three 16-inch discharge pumps with 18-inch suction, 16-inch discharge, the ability to handle a 4.5-inch solid, flow rates up to 17,800 gallons per minute (gpm), heads up to 240 feet, and efficiency up to 85 percent. These pumps were combined with one 12-inch discharge pump with a 14-inch suction, 12-inch discharge, the ability to handle a 3-inch solid, flow rates up to 9,000 gpm, heads up to 200 feet, and efficiency up to 84 percent.
The distributor also used several on-call 4- and 6-inch discharge pumps to dewater Portage Creek. The system bypassed the flow from upstream around the work site and back into the creek below the ongoing mitigation. The pumps were able to handle significant solid sizes because of the unpredictable nature of items that could be found in the creek and the amount of potential plugging solids in the creek bed. The pumps were driven off diesel engines and housed in sound-attenuated packages.
Image 3. The pumps used for the Portage Creek project have sound-attenuated enclosures, as seen from the discharge side.