In the aftermarket business, part replication is not enough. Precision engineering combined with the latest technology are essential for manufacturing high-quality parts. A main boiler feed pump at a Midwestern United States power plant was built in 1967 using sand casting and wooden patterns, now considered outdated technology. Even though the pumps received refurbishment every six to eight years, the pumps continued to have low performance as well as vibration issues. Using all its resources—including casting simulations, 3-D models, up-to-date foundry casting techniques and considerable engineering data—an engineering and repair services company fully manufactured a complete element, performed sophisticated testing in the Pumps Test Lab Approved Program (PTLA) certified test lab, and returned the pump to operation within just 12 weeks. This project involved the manufacture of a complete first stage twin volute and a description of the latent defects. The pump suffered from ongoing vibration issues which were caused by pressure pulsations at vane frequency. To improve the vibration levels, hydraulic analysis and redesign were required to develop a new, improved design. This project has been divided into two articles. The first is the manufacturing of the twin volute and the second is the design of a new impeller.
Power pump performance improved with redesign of the first-stage, double-suction impeller and twin volute.
Hydro, Inc.
06/26/2017
Image 1. A received bundle showing failure in the twin volute stage piece. The aftermarket company received the internal element and casing (pump bundle, or element) of the pump. (Images and graphics courtesy of Hydro, Inc.)
The first-stage twin volute is a complicated casting, which failed during operation as a result of poor design.
The engineering and repair services company re-engineered the casting by using sophisticated engineering and 3-D modeling, along with simulation software and 3-D sand printing.
In addition, the company identified the opportunity to improve the performance of the pump by redesigning the first-stage double-suction impeller. To improve vane passing frequency, the first-stage double suction impeller was redesigned with staggered and split vanes.
The company’s aftermarket services capability provided a completely new replacement element for this high-energy boiler feed pump and also redesigned the castings to eliminate the original latent defect in the casting design.
The company provided sophisticated hydraulic engineering improvements to increase the mean time between repairs (MTBR) of the newly manufactured element.
Image 2. Root cause analysis showed that metal chaplets used during manufacturing initiated the failure mechanism.
Chaplets are usually comprised of different metallurgy from the metal being poured and can create a weak area if left in place. Image 2 shows areas that were either utilized for chaplets or are core sand clean-out plugs, which were excavated and welded.
The engineers eliminated the need for chaplets during the pouring process by using 3-D technology, which allows for the manufacturing of the cores in a hybrid design that will lock them in place inside the mold. By using this method, the sophisticated technology averages the wall thickness, minimizes core shift and minimizes welding. The volute areas were examined by the bore scope and properly cleaned.
Figure 1. Data was captured using scanning techniques and the twin volute was modeled in CAD.
Figure 2. CFD analysis performed for both extreme and optimum condition
Figure 3. Temperature gradient
Figure 4. Gating and risers design and sand mold design
Image 3. (left) Rough casting and (right) casting after machining and the final inspection
Read the second part of this series here.